Waive Not, Want Not: Waivers and Releases on California Construction Projects
California is one of a handful of states (12 to be exact) which have statutory mandated waiver and release forms for construction projects.
So here’s what you need to know before you sign one (or two, or three).
What are California’s statutory waiver and release forms?
California has four statutory waiver and release forms for construction projects.
Which form applies depends on two things: (1) whether it is for progress payments or final payment; and (2) whether it is provided before or after you have been paid.
The four waiver and release forms are:
- Conditional Waiver and Release on Progress Payment
- Unconditional Waiver and Release on Progress Payment
- Conditional Waiver and Release on Final Payment
- Unconditional Waiver and Release on Final Payment
They may sound similar, but they’re not, as shown below:
How are the waiver and release forms supposed to be used?
The waiver and release forms are intended to be used when progress payments and final payment are made on a construction project. By signing a waiver and release form you are waiving your right to record a mechanics lien, file a stop payment notice or make claim on a payment bond once you are paid.
Are the waiver and release forms limited to certain types of projects and are they required to be used?
The waiver and release forms can be used for both private and public works projects. Moreover, while they are not required to be used, if you do require that a release to be provided in connection with payment, then you must use the statutory waiver and release forms “in substantially” the same form as provided under statute.
Who signs the waiver and release forms?
Waiver and release forms are often required by project owners from their direct contractors. Conditional waiver and release forms are required before payment. And unconditional waiver and release forms are required after payment.
Waiver and release forms may also be required by direct contractors from their subcontractors and material suppliers, and from subcontractors and their material suppliers from their second-tier subcontractors and second-tier material suppliers, and so on.
It is not unusual for a project owner to require their direct contractors to provide waiver and release forms for themselves (i.e., the direct contractor) as well as from subcontractors and material suppliers of every tier working under a direct contractor.
How do the waiver and release forms work?
The waiver and release forms are intended to be used together.
As an example, suppose you are a direct contractor performing work for a project owner. On your first progress payment, the project owner may require that you provide a Conditional Waiver and Release Upon Progress Payment together with your payment application as a condition of payment. On your second progress payment, the project owner may require that you provide an Unconditional Waiver and Release Upon Progress Payment for the first progress payment and a Conditional Waiver and Release Upon Progress Payment for your second progress payment as a condition of payment, and so on. When you reach the point of final payment, the project owner may require that you provide a Conditional Waiver and Release Upon Final Payment as a condition of payment and an Unconditional Waiver and Release Upon Final Payment once payment has been made.
Here’s an illustration assuming a hypothetical project with four payments:
Can I use my own waiver and release form or change the language in the waiver and release forms?
Generally no. California’s waiver and release forms are mandatory, and while you can adjust the language in the forms, beware if you do. The Code sections which outline the language required in the waiver and release forms (Civil Code sections 8132, 8134, 8136 and 8138) state that a waiver and release “shall be null, void, and unenforceable unless it is in substantially the following form . . .” (emphasis added).
How do you complete the waiver and release forms?
The “fillable” sections of the waiver and release forms are generally the same for the Conditional Waiver and Release Upon Progress/Final Payment and Unconditional Waiver and Release Upon Progress/Final Payment.
For the Conditional Waiver and Release forms:
- Name of Claimant: This would be your company.
- Name of Customer: This would be the company with whom your company has a contract to perform work.
- Job Location: The location of the project site.
- Owner: The name of the project owner.
- Through Date: This is the last date in which labor, materials and/or equipment was furnished under your pay application. So, for example, if the waiver and release is for your March 1, 2015 pay application, it would be through the last date in which labor, materials and/or equipment was furnished as indicated in your March 1, 2015 pay application.
- Maker of Check: Typically, this is the company with whom your company has a contract. However, it could be another company if it’s a joint check.
- Amount of Check: Again, typically, this is the amount of your pay application for the month.
- Check Payable to: Again, typically, this your company, although it could be your company and another company if it’s a joint check.
- Exceptions: Item (3): This section should be filled out if you have not been paid a previous progress payment.
- Claimant’s Signature: Signature from someone at your company authorized to sign the waiver and release form.
- Claimant’s Title: The title of the person signing the waiver and release form.
- Date of Signature: The date the waiver and release form was signed.
For the Unconditional Waiver and Release forms:
- Name of Claimant: This would be your company.
- Name of Customer: This would be the company with whom your company has a contract to perform work.
- Job Location: The location of the project site.
- Owner: The name of the project owner.
- Through Date:This is the last date in which labor, materials and/or equipment was furnished under your pay application. So, for example, if the waiver and release is for your March 1, 2015 pay application, it would be through the last date in which labor, materials and/or equipment was furnished as indicated in your March 1, 2015 pay application.
- Claimant has received the following progress payment: Amount of the progress payment received.
Note: Remember a check is simply a promise to pay. As such, for those that are cautious, an unconditional waiver and release form should not be provided until payment is actually received, which in the case of a check, is when the check clears the bank upon which it is drawn.
- Claimant’s Signature: Signature from someone at your company authorized to sign the waiver and release form.
- Claimant’s Title: The title of the person signing the waiver and release form.
- Date of Signature: The date the waiver and release form was signed.
If I’m a contractor and I complete and sign a conditional waiver and release form am I giving up all my rights?
No. First, with a conditional waiver and release form you are only giving up rights once you are paid. However, an unconditional waiver and release form is just that . . . unconditional . . . and once you sign it you are indicating that you have been paid in exchange for giving up your rights.
Second, with respect to both the conditional and unconditional waiver and release forms you are only giving up your statutory construction payment remedies, namely, the right to record a mechanics lien, serve a stop payment notice and make a payment bond claim. You are not giving up rights to sue: (1) for retention (in the case of waivers and releases for progress payments); (2) for extra work in which you have not been paid; (3) for unpaid progress payments you specifically identify in the conditional waivers and releases; (4) for rescission, abandonment and breach of contract claims; and (5) for disputed claims you specifically identify (in the case of waivers and releases for final payment).
If I’m a project owner and a contractor refuses to provide an unconditional waiver and release form, what happens?
First, you shouldn’t have this problem when it comes to progress payments because you are presumably going to require an unconditional waiver and release upon progress payment form for the previous payment as a condition of receiving the next payment (see illustration above).
Where this problem occurs most frequently is when it comes to the unconditional waiver and release upon final payment because, at that point, you’re not holding any money as an incentive for your contractor to provide an unconditional waiver and release upon final payment (see illustration above).
But fret not. Even if your contractor refuses to provide you with an unconditional waiver and release upon final payment, you’re covered if the contractor provided you with a conditional waiver and release upon final payment. This is because a conditional waiver and release, whether it’s for a progress payment or final payment, effectively becomes an unconditional waiver and release by its terms upon the contractor’s receipt of payment.
Share this:
Like Loading.
Related
Categories: Conditional and unconditional waivers and releases, Progress payments, Retention
144 Responses to “Waive Not, Want Not: Waivers and Releases on California Construction Projects”
- AIA Releases State-Specific Waiver and Release Forms | California Construction Law Blog | Nomos LLPAugust 19, 2022 […] those who aren’t familiar with California’s waiver and release statute, they provide a mechanism by which higher-tiered parties can protect themselves from mechanics […] Reply
- Larissa March 17, 2022 I am filling out a CA Conditional Waiver and Release On Progress Payment form, this is our first payment on this contract. This GC has their own calculation form to fill out that shows they hold a 10% retention.
When filling out the “Amount of Check” on the waiver do I put the amount before the retention or less retention? Reply
- Garret MuraiMarch 17, 2022 Hi Larissa. You should put down the amount of the check you are to receive less retention. Reply
- dlhackbartgmailcomSeptember 27, 2021 Hi, I have a related but slightly different situation. I’ve already paid my contractor invoices in full but after re-reading the contract, he explicitly was to invoice me daily. This was discussed and purposely added to the contract. After paying some of the invoices, I realized he didn’t invoice me per the contract and actually invoiced me weeks and months later, but I paid them. TWO questions: does payment in full of an invoice deem me to have waived my right to invoke the daily invoice mandate and therefore claim I’ve overpaid him, and since I owe him money on another project, unrelated but I would like to pay him, can I essentially claim those monies back saying they were overpayments? (There is good reason ethically for me to do so but wondering legally) in CA… Maybe the same question but am hoping your response will clarify. Thanks… Dave Reply
- Garret MuraiSeptember 28, 2021 Hi Dave: An argument can be made by the contractor that you waived the right to require daily invoices based on the past conduct of the parties, but the better argument, is that the contract says what it says and it says that invoices were to be generated daily. As to whether you overpaid the contractor, as opposed to the parties simply not following the contractual invoicing requirements, I can’t speak to that. As to withholding money for this alleged overcharge on another project the contractor is working with you on, I wouldn’t. It would likely be considered “self-help” which is frowned upon by courts since they are two separate projects presumably with two separate contracts. Reply
- ACW April 22, 2021 Hi Garret, We are a contractor in California and request releases from several out of state suppliers. We have one supplier that provides releases with the same verbiage as the required CA release, except it does not include the “NOTICE TO CLAIMANT” portion at the top of the release. Is the supplier release still valid if all other information is the same? Thank you,
ACW Reply
- Garret MuraiApril 22, 2021 Hi there. The Civil Code sections which include the waiver and release language provide that a “waiver and release shall be null, void, and unenforceable unless it is in substantially the following form . . .” So, a waiver and release does not need to be exactly in the same form as what is contained in the Civil Code although it is of course good practice to use the exact language as used in the statute. No case that I am aware of has addressed whether not including the “Notice to Claimant” language would invalidate a waiver and release, although my guess, is that it would not. Reply
- SV March 18, 2021 Do these release and waiver forms apply to contracts for professional services/design consultants or only to construction contracts? Thanks. Reply
- Garret MuraiMarch 18, 2021 No, they only apply to construction contractors. Reply
- Peter M December 1, 2019 Hi Garret, Great article. I was wondering do you know whether conditional lien waivers can be used after work has been completed and in effect, toll the 90 day from actual completion of construction timeline? Here’s the scenario – contractor completes work for owner on January 1, 2020. Owner doesn’t have the cash to pay contractor immediately but also does not want liens recorded against his property. Owner and contractor then figure out a payment plan and agree to sign a conditional lien waiver that provides that contractor will be paid x on February 15, 2020. The money is not paid and contractor decides he wants to record a lien against the property. Does that mean the 90 day clock starts running on February 15, 2020, or does the contractor only have 45 days remaining following the last day of work being carried out on the construction site on January 1, 2020? Thanks! Reply
- Garret MuraiDecember 4, 2019 Hi Peter. A waiver and release wouldn’t effect completion deadlines. You may want to read our article here – https://calconstructionlawblog.com/2015/05/04/it-aint-over-till-its-over-why-project-completion-in-california-isnt-as-straightforward-as-you-think/Reply
- Edwin Benavides April 10, 2018 Hi Garret,
Thanks for this explanation.
I’m I general contractorin California and I have a question for you i hope you can help me. I spoke with a friends and he is a general contractor in other State, my friend use a lien waiver stamp in any check to prevent any lien from subcontractors.
Can I use a unconditional lien waiver stamp in CA ? Please let me know. Thank you for your time !. Reply
- Garret MuraiApril 15, 2018 Can’t do it in California. A subcontractor would need to sign a statutory waiver and release. Civil Code section 8122 provides that “[a]n owner, direct contractor, or subcontractor may not, by contract or otherwise, waive, affect, or impair any other claimant’s rights under this part, whether with or without notice, and any term of a contract that purports to do so is void and unenforceable unless and until the claimant executes and delivers a waiver and release under this article.” Reply
- Heather February 27, 2018 Hi Garret,
I’m interested to hear your take on how to handle a conditional final. Let’s say a general contractor has 3 outstanding invoices with us, January, February, and Retention. Pretty much every GC asks for a conditional final with the retention billing. A conditional progress allows you to list unpaid progress payments as an exception (I could generate a conditional progress through February and list January’s open amount in the exceptions), but a conditional final does not have that option. It’s my understanding that a conditional final essentially releases all your rights once payment received. If the conditional final only listed the retention amount as the amount due and didn’t include the open progress payments, would that leave us vulnerable to being short-paid? Thanks for your input! Reply
- Garret MuraiMarch 15, 2018 Yes, it would. The better strategy would be to include in the amount section all unpaid amounts. Reply
- Samuel May 9, 2018 Garret, What recourse, if any, do I have to collect unpaid progress payments if I didn’t include them in the exclusions when furnishing a conditional waiver and release on final payment?
- Garret MuraiMay 10, 2018 You could file suit for breach of contract but you wouldn’t be able to record a mechanics lien, serve a stop payment notice, or file a payment bond claim. Basically, you would still have your common law remedies but no statutory remedies.
- Andy January 30, 2018 Hello, I hope you all are doing well,
I ‘m contractor for public projects, i have a project manager that hires employee and got “Unconditional Waiver and Release on Final Payment” form from all employees and in the form mentioned : This document does not affect any of the following: “No Exceptions” My concern is, he wont pay them in full and put money in pocket and now I’ve started investigate to know whats happen. please let me know if employees sign this form,can they sue against our workers compensation? is there any form that i can ask my manager to sign that form to make sure he will be responsible if something happen or no? I appreciate for the time. Thanks Reply
- Garret MuraiMarch 15, 2018 There’s a couple of things going on here. First, the statutory waivers and releases only apply to payment claims not workers’ compensation claims. So, an unconditional final would not impact an injured worker from making a workers’ compensation claim. Second, the statutory waivers and releases only effect statutory claims such as the ability of a worker to record a mechanics lien, serve a stop payment notice, or make a payment bond claim. They do not alter an employee who has not been paid from suing their employer for unpaid wages. Reply
- Belinda December 13, 2017 Hi Garret, On Change Order Invoices, should a Conditional Progress be provided to the General Contractor or a Conditional Final? Reply
- Garret MuraiDecember 13, 2017 Hi Belinda. Change orders add to or reduce the overall scope of work and can include an addition or reduction at any time during the project. If the work performed includes change order work but it is not the final work being performed for the overall project than a conditional waiver and releases upon progress payment should be used. Reply
- Tony Laurent September 15, 2017 Hypothetical Scenario where i am the GC.
Lets say a Bob the Builder (My Subcontractor) invoices me for $100 and provides a conditional progress waiver. He also submits a conditional progress release from ABC materials (Bob’s Supplier) in the amount of $10. We cut two checks, Check 1: $90 to Bob the Builder
Check 2: $10 to Bob the Builder & ABC Materials
Now i’ve asked Bob the Builder for his unconditional progress release and he gives me one for $90. I tell him i need one for $100 because that is the amount that was paid to him through both checks. He argues that he only has to provide a release for the amount that was paid to him directly. My argument is that both checks were paid directly to him and he signed the joint check over to his supplier. i also state that his unconditional should match his conditional unless we have short pad him. He says he isnt signing anything stating that he’s been paid more than what was in his account.
Who is right? If i am right, where can i find something in writing supporting that i am right? Reply
- Garret MuraiSeptember 18, 2017 Hi Tony. You might try a career writing law school practice questions. I’ll try to answer in proper law school format: IRAC. Issue: Does Bob the Builder have to provide GC with an unconditional waiver and release for $100 if GC pays Bob $90 and pays Bob’s supplier $10 by joint check. Rule: Under Civil Code 8124, a conditional release is deemed to be an unconditional release upon payment of the amount contained in the conditional release whether by direct payment or by joint check. Application: If the proper statutory waiver and release forms are used, and GC pays Bob by direct check and Bob’s supplier by joint check endorsed by Bob, then Bob and Bob’s supplier’s conditional releases are deemed to be unconditional releases. Conclusion: Tony, you’re right, but you don’t need an unconditional release. Of course, you can always require that Bob provide an unconditional release for the first payment as a condition of Bob receiving his second payment, hypothetically speaking. Reply
- Erin Ellis October 5, 2018 Hi Garret – I realize this question is more than a year old, but I have a specific question on exactly this topic. Hoping you can clarify: I am a GC and have a client that insists on cutting joint checks to me, my subs and their suppliers. (As a GC, I am seasoned in joint check writing, I cut mostly joint-checks to my subs and suppliers on all other projects.) But this is the only client I’ve ever had in 20 years that does this. The big issue though, is that they want all releases to match exactly to the checks they cut. Using the Bob the Builder example above (I am Bob the Builder in this case), they actually write three checks:
Check 1: $50 to Bob the Builder
Check 2: $40 to Bob the Builder & XYZ Drywall
Check 3: $10 to Bob the Builder & XYZ Drywall & ABC Materials I provide them with three releases:
UP from Bob the Builder for $100
UP from XYZ Drywall for $50
UP from ABC Materials for $10 Obviously, the totals don’t match the checks written, but rather correspond to the contractual relationship. I am releasing $100 of my contract to the client, and XYZ Drywall is releasing $50 of their contract with me ($10 of which was paid to ABC Materials). What this client is demanding I provide is:
UP from Bob the Builder for $50
UP from XYZ Drywall for $40
UP from ABC Materials for $10 Which is correct? And, is there a Civil Code or statute that clearly defines this issue that I can point to for purposes of clearing this up? Thank you!
- Garret MuraiNovember 7, 2018 The Code doesn’t specify. But I would say your way is cleaner. Plus, why would the owner care, with your way, at least on paper, the owner is getting larger $ releases?
- Robert September 1, 2017 Typically GCs that are funding for a specific month request an unconditional progress from our material suppliers through the previous month that they are funding (i.e., the GC is funding for a June invoice & requests a vendor’s unconditional progress through May to show that we paid our vendors through May with the funds we have received for our May invoice). More and more lately we have been asked to provide releases from our vendors for the month that the GC is funding (i.e., the GC is funding for August & is requesting a vendor’s release through August). To me, this seems out of sorts as most contractors fund their vendors when they are funded by the GC so most likely the vendors would be providing a conditional progress since we haven’t been funded yet so they we have not in turn funded them and a joint check would be issued. Has something changed in 2017 that is making this become the standard request with regards to releases? Reply
- Garret MuraiSeptember 5, 2017 Hi Robert. Nothing has changed legislatively to California’s waiver and release statutes. Interestingly, though, this is the second time this situation has been mentioned to me recently, although the other situation involved a construction lender demanding unconditional releases before payment was made. To me, this practice is not what the legislature intended, and in fact makes “you” the the financier because most sophisticated subs will not provide you with an unconditional release unless you have paid them first. Reply
- L.H. August 25, 2017 “preliminary notices need to be served no later than 20 days of the date they last performed work.” I thought a preliminary notice had to be served within 20 days of the START of work or furnishing materials? Am I misunderstanding something? Thank you and thank you for this post, makes things regarding conditional/unconditional waivers much clearer. Reply
- Garret MuraiAugust 25, 2017 Hi L.H. Thanks for reading. I didn’t see the statement you quoted in the article. Perhaps it was from another article? Nevertheless, it is true that a preliminary notice must be served no later than 20 days of the date a contractor/subcontractor/supplier has last performed work. Of course, this is the statutory requirement, not a best practice. The best practice is to serve a preliminary notice no later than 20 days after “first” starting work, as you state, since can only make a monetary claim through your statutory remedies (mechanics lien, stop payment notice, etc.) for work performed within 20 days of serving a preliminary notice when one is required. I say “when one is required” because direct contractors do not need to serve a preliminary notice unless a construction lender is involved in a project. All of this is a long way of saying that you’re right. Reply
- Eric June 29, 2017 Hi, excellent info as always! If I am the owner of a project, and I require a subcontractor (Painters for example) to sign a conditional waiver, and I additionally require of them that all of their subcontractors and material supplier sign a conditional waiver, how do I know that they have fully represented resented me with all of the waivers from their subs and material suppliers? Is there any way I am covered if they forget to (or intentionally do not supply) waivers from one of their subs or material suppliers? Thank you as always! Reply
- Garret MuraiJune 29, 2017 Hi Eric. A few things you can do: (1) include a requirement in your construction contract that, with each pay application, the general contractor provide a list (updated as necessary) of lower-tiered subcontractors and suppliers. This will provide you with important information on potential lien claimants; (2) review your project file to see who you have received preliminary notices from. Subcontractors and suppliers can only lien your property if they have first served you with a preliminary notice; (3) ensure that your construction contract provides at least 30 days (45 days is better) for you to make final payment to the general contractor and don’t pay your general contractor until close to that deadline. This will provide sufficient time for you to wait and see if you receive any preliminary notices from subcontractors and suppliers who perform work toward the end of the project since preliminary notices need to be served no later than 20 days of the date they last performed work. Reply
- Eric June 29, 2017 Thank you! In what format are General or subcontractors responsible to preliminarily serve a notice to me? In other words, do they need to notify me in writing to my address on our contract? In a public record forum somewhere? Other? I’m just trying to figure out all of the places I would need to look for a notice from a painter, a drywaller, etc. Thank you again… Your blog and information are absolutely excellent!
- Garret MuraiJuly 10, 2017 Hi Eric. The Code does not specify, however, they will likely be served at either: (1) the address in your contract: or (2) if you are a business entity, the address listed with the California Secretary of State.
- Eric July 10, 2017 Thank you!
- Twala June 22, 2017 We order carpet form a vendor and when ever we need to get a Lien release fro them they always ask me to provide them with the forms and ill it out. If they issue the prelien shouldn’t they be the ones doing the forms not me. Reply
- Garret MuraiJune 26, 2017 Twala there’s nothing under the waiver and release statute which addresses who is responsible for preparing waiver and release forms. If you would like your vendor to prepare the forms you can always specify that in your contract or purchase order with the vendor. Reply
- Brad June 15, 2017 …So if you file an Unconditional Waiver and Release in error when it should have been a Conditional Waiver and Release, is there a way to correct the mistake? Reply
- Garret MuraiJune 15, 2017 There’s nothing in the statute that allows you to do this, but if you communicate that it was furnished in error in a timely error you increase your chances that a court, should it ever come up in litigation, will excuse you. Reply
- Eric June 1, 2017 Hi, excellent blog! Very informative. If I hire a drywall contractor (or HVAC, electric, etc), and they don’t pay their materials suppliers or employees, am I exposed to liens even if I had the drywall contractor sign the appropriate lien waivers? I am in CA. Thank you! Reply
- Garret MuraiJune 1, 2017 Hi Eric. Yes, you should receive waivers and releases from material suppliers, though industry standard is not to receive waivers and releases from employees. The reason why you should insist on waivers and releases from material suppliers (and any lower tier sub) is because a waiver and release from the party you hired (i.e., the drywall contractor) only waives and releases the drywall contractor’s rights to record a mechanics lien, serve a stop payment notice and make a bond claim, not any lower-tiered parties. Reply
- Eric June 1, 2017 Thanks very much! So, said another way, if I hire a drywall contractor and they do all of the work and sign a lien waiver, the company that sold the actual gypsum board to my drywall contractor could come after me with a lien if my drywall contractor didn’t pay the gypsum supplier?
- Garret MuraiJune 1, 2017 Exactly.
- Belinda April 10, 2017 I just received payment on a change order and the GC sent an Unconditional Final along with the payment to be signed and returned to them. However, I have not been paid in full on this job. There are two remaining outstanding invoices that the GC needs pay on this project. Should I provide the Unconditional Final that was sent with their payment or an Unconditional Progress for the change order? Reply
- Garret MuraiApril 16, 2017 Hi Belinda. You would want to send an unconditional Progress. Reply
- Michael April 9, 2017 Can laborers file mechanics liens for remedial work (i.e. the prime contractor messed something up and fixes it)? As there is no payment in the first place, that can be withheld conditional on signed releases, it appears that the release system fails to work as intended. A similar scenario would be the contractor needing two or three times the quoted price of a fixed price project to accomplish the work, due to “inefficient” allocation of labor and capital, to put it mildly. Both scenarios sound theoretical, but are actually very real. Reply
- Garret MuraiApril 10, 2017 Hi Michael. Yes, laborers can record mechanics liens for labor performed whether remedial or otherwise. Reply
- Judy MasonApril 4, 2017 We have completed a job contracted directly with a homeowner. He has paid us and we are going to sign and give him an unconditional final release waiving our rights to collect any more money from him. Is there something that we can get him to sign for us, stating he has accepted our work as complete and competent and therefore gives up his right to come after us for anything more? In other words, do these release waivers go both ways? What is there to protect the contractors from “crazy”? Reply
- Garret MuraiApril 8, 2017 Hi Judy. The statutory waivers and releases are intended to “waive” and “release” your mechanics lien, stop payment and payment bond rights in exchange for payment not a homeowner’s rights with respect to your work. If you would like to limit a homeowners rights with respect to your work you would have to either include a provision in your contract or shorten the statute of limitations, both of which can be risky as being found to be void as to public policy, since California has a 4 year statute of repose for patent defects and a 10 year statute of repose for latent defects. Reply
- Michael March 13, 2017 The CSLB refers to “laborers” in addition to “subcontractors” in most of their informational material (“A mechanics lien is a “hold” against your property, filed by an unpaid contractor, subcontractor, laborer, or material supplier”…)
What is the definition of “laborer”, in contrast to a “subcontractor”?
Would “laborers” include employees of the contractor, and can employees file liens on the homeowner’s property?
My construction contracts specifies “no subcontractors”. Are day laborers considered subcontractors? Reply
- Garret MuraiMarch 13, 2017 Hi Michael. Laborers are individuals who perform work on a project. They are typically employees of the contractor, but if your want to be technical, they could also be union laborers who provided under a collective bargaining agreement. Reply
- Michael March 13, 2017 I read your article with interest, and I was surprised that as a homeowner I left myself vulnerable to double payments with all my past home improvement contracts.
Additionally, while I am very sympathetic to the idea that everybody in the value chain gets paid what they are entitled to, I am having a hard time how, for practical purposes, the homeowner can assume the role of collection enforcement for all n-tier subcontractors and suppliers (n >= 1). The way I read it, not only would it appear that this would entail a crazy amount of bureaucracy and paperwork if done properly, if every sub-sub[…]-contractor or supplier down to every tier in the supply chain needs to exchange lien waivers with the homeowner at every stage in the project, and homeowner’s progress payments split into the respective contributions attributable to every n-tier subcontractor, and joint payment checks be processed and signed; but also, I am having a hard time understanding how the homeowner would gain knowledge of who are the 2nd and higher tier subcontractors and suppliers (even if direct subcontractors were listed in the contract, which never was the case for me).
I recently had a patio cover erected that required steel beams, and the GC hired a painter, among others. How would I know where the GC bought the steel beams? Even if I knew, how would I know where the steel manufacturer/contractor bought the iron ore, and where the painter bought the paint, and how would I control whether all those entities and suppliers got paid whatever they are entitled to according their supply or service contracts, that I am not even a party to?
If I don’t, am I vulnerable to double payment? None of my past home improvement contracts in CA specified lien waivers as a requirement for payments. Couldn’t an unscrupulous contractor easily collude with their suppliers and extract double payments from homeowners? I would appreciate if you could shed some light on the practical implementation of the legal framework. Reply
- Garret MuraiMarch 13, 2017 Hi Michael. You’ve posed a lot of questions today. The short answer is that, with the exception of a contractor who you are directly in contact with (and who you would obviously know the identity of), as for other lower-tiered parties you would know who they are because in order for them to record a mechanics lien or serve a stop payment notice they would have to serve you with a preliminary notice which identifies who they are, what work or materials they have or will be providing, and an estimate of the value of that work and materials. There may be others who perform work or provide materials, but if you don’t receive a preliminary notice from them you don’t have to worry about them, because they need to serve you with a preliminary notice as a condition of recording a mechanics lien on your property or serving you with a stop payment notice. Reply
- Michael March 13, 2017 Point well taken. What an excellent blog! I thought along the same lines when reading your article. However, I also read your article from April 1st 2013 on preliminary notices, which allow liens covering up to 20 days prior, and combining the information from your articles, it would appear that there is a 20 day window of vulnerability for the homeowner, while the homeowner waits hoping for his or her progress or final payment to “trickle down” the tiers in the value chain (OR NOT, which he has no control over). I’m sure I missed something and there is a solution to this.
- Garret MuraiMarch 13, 2017 Thanks Michael. You are correct that there is a “potential” 20-day window of vulnerability. For example, say you are in your last month of construction and a painting subcontractor is hired by the general contractor to paint the interior (or exterior) of a house, which is typically one of the last things done, and the painting subcontractor starts on the first day of the month and finishes on the 10th. Further, assume that the general contractor sends a final invoice on the 15th. Because the painting subcontractor has 20 days to serve a preliminary notice, if you pay the general contractor before the 20th, you may not receive a preliminary notice from the painting subcontractor and know that you should request a waiver and release from that subcontractor. The solution to this potential problem is to wait at least 20 days to pay the final invoice (the Code gives you 45 days) to see if you receive any last minute preliminary notices before paying the final invoice. The one risk you will always have though (the legislature for some reason chose not to address this) is that a laborer is not required to serve a preliminary notice before recording a mechanics lien. Thus, there is the potential that a laborer can record a mechanics lien after you’ve made your final payment and within 90 days of completion of the project which is the deadline to record a mechanics lien. The 45-day final payment window, unfortunately, won’t help you here.
- Nick March 2, 2017 Hi Garret, I have a question about the bracketed section below form the waiver: NOTICE TO CLAIMANT: THIS DOCUMENT WAIVES AND RELEASES LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS UNCONDITIONALLY [[AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS]]. The sentence “and states that you have been paid for giving up those rights” makes it sound like the customer should be paying an additional fee to the contractor to give up those rights, not that the payment for services was made. Am I interpreting this incorrectly? I’m trying to figure out why a contractor would sign this and give up their rights without an incentive. Thanks. Reply
- Garret MuraiMarch 2, 2017 Hi Nick. Thanks for reading. The bracketed section could be better stated but it’s the language required under the statute. The bracketed language simply means that by accepting payment the contractor no longer has the ability to record a mechanics lien, serve a stop payment notice or pursue a payment bond claim for the amount received. Reply
- Nick March 2, 2017 Thanks for the response Garret. So why sign the document if payment has been made and there is no outstanding balance that would create a lien?
- Garret MuraiMarch 2, 2017 Hi Nick. First, just to be clear, the statutory waivers and releases are signed by contractors not project owners. I just want make sure there’s that baseline understanding because your question might suggest some confusion on that point. Having said that, the reason why project owners want their contractors to sign the statutory waivers and releases is so that “if” a contractor records a mechanics lien, serves a stop notice or makes a bond claim the project owner has a document it can present to a court showing that the contractor waived its rights to do so.
- Jan Christensen March 6, 2017 We are a subcontractor and have had a few GCâs that are terrible at paying. I have had to alter invoices to a lower amount just to get a payment and that is irritating enough but what I would like to know is #1) can we refuse to sign their version of an Unconditional on Progress that does not show that they still owe money within the Through Date of that release? There were approved Change Orders and several Extras that are still outstanding so I noted those on our Conditional releases as well as any Unconditional releases I have sent to them. BUT, when we go to pick up the checkâ¦they bring out THEIR version of an Unconditional which is nice and clean and says we have been paid in full through a specific date and it is just not accurate. We feel forced to sign said release in order to receive the check. I believe they want this clean (but inaccurate) lien release so they can keep the owner happy (yet in the dark) about what is really happening. #2) What are our rights as far as work we Know we have completed, yet the GC says it hasnât been approved? #3) Shouldnât we always write in what is still outstanding if it is within the âthrough dateâ period? We are owed money on July 2016 invoices for Extra work and I donât think they want the owner to see this list I have written on the releases. Thanks for all your wonderful knowledge Jan Christensen Office Manager jan@championsplumbing.com Champion’s PLUMBING & HEATING, Inc. 281 Arthur Road Martinez, CA 94553 Ph 925-372-0881 Fax 925-372-9448
- Garret MuraiMarch 13, 2017 Hi Jan. As to the Unconditional Waivers and Release on Progress Payment forms, by signing the form, you are agreeing that you have been paid through the “through date” with the exception of retention, extras and certain contract rights, only. Second, with respect to your rights as to work completed but which the GC has said hasn’t been approved, ideally, you should not be doing any work unless you have a change order or your contract permits change directives. If you haven’t been paid, then depending on your situation, your recourse would be to record a mechanics lien, serve a stop payment notice (this is less typical on private works job), or file a lawsuit. Finally, with respect to writing in the amount of extra work performed, you can, but it is not necessary, since each of the waiver and release forms either reserve your right to make a claim for extra work or, in the case of the Unconditional Waiver and Release on Final Payment, allows you to indicate the amount of your extra work claim.
- Christian February 22, 2017 Garrett,
I am a homeowner (CA) and my contractor asked me to sign an unconditional waiver form after the project is done. I did not pay the final balance due to several damages to my kitchen cabinets. They made extra holes in the cabinets that it shouldn’t be there, and never replace any of them in the process. My question is, do I have to pay the final balance? Reply
- Garret MuraiFebruary 24, 2017 Hi Christian. If by “unconditional waiver form” you mean the statutory waiver and release for final payment, it’s something that the contractor signs, not the project owner. Reply
- Rene Ward February 21, 2017 Hi,
My client is asking us to put the amount invoiced less retention on our release. For example I billed for 10k. She wants us to list 9k on waiver. No one has ever asked for waivers like this. What is the standard and correct way to send them. Reply
- Garret MuraiFebruary 24, 2017 Hi Rene. Isn’t the amount invoiced already less retention? So, for example, if you performed $10k worth of work, and retention is 10%, then the amount invoiced should be $9k. Therefore, you should provide a conditional waiver and release on progress payment for the $9k, and once that amount is paid, you would provide an unconditional waiver and release on progress payment for the $9k received. Reply
- Marisa February 17, 2017 I am a sub and have a GC asking for lower tier suppliers waiver. They want total amount paid & outstanding amount to date. It just so happens that I am paid in full, sometimes i may not be at the time of the waiver but why do have to tell the GC what I paid for my materials. Reply
- Garret MuraiFebruary 20, 2017 Hi Marisa. Unless your contract with the GC requires that you provide this information you’re not required to. Reply
- Steve Jenkins February 8, 2017 Garret, I live in CA and contracted with a window company for a project that included bay windows and several other windows and sliding doors. The bay windows originally brought (12/15/16/) for installation didn’t even meet egress codes and were the wrong dimensions compared to what they were replacing. I informed the window company owner that he would need to come out again to get it right. He then informed me this time that he wouldn’t be able to replace my existing bay windows with ones of the same size. As a result, I then told him he would be responsible for rebuilding the decorative brick wall that rested under the bay window to ensure it extended only as far as the new bay window. He agreed. He then reordered the windows to ensure they met egress codes. When these windows arrived in early January, after the installers mounted one set of the bay windows and demo’d the brick wall under both of them, I opened up the windows and noticed that these windows STILL didn’t meet the CA egress codes. I told the crew to stop and get the owner on the phone. After meeting with him two more times, it appeared we finally found a solution to the windows but then I stopped hearing from them and I sent them a Registered Letter informing them that because of the negligence and inability to deliver a product that resembled my current bay windows, I was only to pay him 50% of the remaining balance. After speaking with the contractor and confirming he received my letter and understood my intentions regarding the final payment, I want to ensure I have covered myself in terms of any remaining liability because I will be paying a final amount that is different than what is on the contract. Which Waiver and Release Form do I use and is there a PDF template available that I can populate online and then print out to give him as I hand over the final payment? Reply
- Garret MuraiFebruary 16, 2017 Hi Steve. You should ask the general contractor to provide you with an unconditional waiver and release upon final payment on behalf of his company and all subcontractors and material suppliers from you have received preliminary notices. The one thing to note, however, is that a waiver and release only releases mechanics lien, stop payment notice and bond claims, it does NOT release breach of contract claims. Thus, you should ensure you have something in writing whereby the general contractor is agreeing that the final payment you will be making is in full satisfaction of your construction contract with the general contractor. Reply
- Doug January 11, 2017 Garret.. This is an excellent description of the lien waiver process.
I do have one question. We are a subcontractor and typically use suppliers on our projects.
I have a GC that asks us to reduce the amount of our conditional progress releases by our supplier amounts. I have done this a couple of times in the past but it just seems wrong to me.
I believe it is their way of accounting for the joint check dollar amounts to my suppliers and how much our check amount will be.
What do you think of this process? are we giving up lien rights when we do this? Reply
- Garret MuraiJanuary 12, 2017 Hi Doug. Thanks for reading. I agree with you. The conditional waiver and release upon progress payment form includes a section to indicate the amount of the check to be received and the unconditional waiver and release upon progress payment form includes a section to indicate the amount of the check received. A joint check, while jointly payable, is still payable to your company and should be included. The drawback if it is not included as I see it (and it really is more of a drawback for the GC), is that if you don’t include the amounts you owe to your suppliers then it could put the GC at risk that you will come back and say you weren’t paid in full. Reply
- Julie johnson October 28, 2016 I have a situation with a general contractor. We are a sub contractor to the GC. The contract with this GC is a single contract for 9 buildings. We are progress billing them for each building in thirds as it is completed. We send progress billings each month with the pay app, schedule of values and conditional progress release. On our invoice we show a gross billing, retention amount and a net billing. The conditional progress release provided to the GC is for the net billing. I am being asked by this GC to bill 90% only with no retention on the invoice and provide a conditional progress release for the invoiced amount. He is requesting that I submit a conditional final release for the 10% retention with each invoice, even though it is not on the invoice. Normally I provide a conditional final release when the job is complete on all 9 buildings and I am billing for the retention on all 9 buildings and work is complete. I have never provided more than one conditional final release on any of our past projects. My question is can I provide more than one conditional final on a single contract, in this case it would be 9 separate conditional final releases. If so can I put the amount of the previous conditional finals on the disputed line if they have not been paid? We anticipate this project to be complete within two years. He has not been clear if he will be releasing the retention on a per building schedule or waiting until all 9 buildings are complete. Reply
- Garret MuraiOctober 28, 2016 Hi Julie. The statutory conditional waiver and release on progress payment states that it “does not affect” retention. Thus, there should be no issue with providing a conditional waiver for the “net” amount while still identifying withheld retention in the invoice. Providing multiple conditional final releases for retention isn’t necessary. The invoices indicate the amount of retention withheld, the conditional progress indicates the net amount (less retention) owed, and at the end of the project you will submit a final billing (including retention) and provide a conditional final. Reply
- Carmen Escobar October 4, 2016 I have a question. Are we required to get an Unconditional Waiver and Release form back from a Consultant? the consultant is filling out a Conditional Waiver and Release form with their Invoice and Progress Release form. Does a vendor who provides only Blueprint services need to fill out an Unconditional Waiver form? Reply
- Garret MuraiOctober 4, 2016 If the vendor only provided blueprint services you would not need a waiver and release (either a conditional or unconditional) from that company because it couldn’t record a mechanics lien, serve a stop payment notice, or make a payment bond claim in the first place. Reply
- Rebekah September 29, 2016 Hi Garret,
Thank you for all of this useful information! I have a few questions.
I am a CM on a public works project. Is it true that only companies (suppliers, subs) who file a preliminary notice are required to submit waiver & release forms? If so, when you reach the end of their billing, would it normally equal or be close to the amount on the prelim?
Or should the GC collect Conditional waivers from everyone who bills the project?
Our client was asking for $0 waivers from everyone even if they did not bill the project. As you said earlier, it’s difficult to know WHO these should come from if they haven’t billed for anything yet. I am trying to straighten this out for them as I don’t believe they completely understand the process. My other question is, on another project, they have been accepting Unconditional waivers from subs/suppliers without a previous Conditional waiver being sent. Is that sufficient? I wouldn’t think so being that the client would not have anything to compare to. Thank you! Reply
- Garret MuraiOctober 4, 2016 Hi Rebekah. Waiver and release forms are not statutorily required, however, many owners and GCs require them in their contract to protect themselves. Waivers and releases can be required even if a party did not serve a preliminary notice since a party can still make a payment bond claim (if there is one on the job) without having first served a preliminary notice. Waivers and releases may or may not total up to the amount stated in a preliminary notice since change orders (both additive and deductive) occur on a project. And finally, as to unconditional waivers and releases, it is fine to accept unconditional waivers without a corresponding conditional waiver since the unconditional waiver simply provides that the party providing the unconditional waiver has been paid through the “Through Date” (in the case of unconditional waivers on progress payments) or has been paid in full for the entire project (in the case of unconditional waivers on final payment). The only risk in accepting in unconditional waivers only is that you may pay someone but they may refuse to provide you with with an unconditional waiver. Reply
- Garret MuraiOctober 4, 2016 Rebekah, one amendment to what I said above. You do not need to obtain a waiver and release from someone who is not entitled to serve a preliminary notice. So, for example, you don’t need to ask PG&E for a release even though it supplies power to the project because PG&E isn’t entitled to serve a preliminary notice to begin with.
- Christopher LeeSeptember 21, 2016 Hi Garret,
Much appreciated on your assistance regarding lien releases. I have a question. I have provided my second conditional progress that shows an exception amount as I haven’t been paid from the first pay app. We received payment after the second lien release and I provided an unconditional progress showing payment was received for the first pay app. Do I have to send them a revised second lien release to remove the exception amount? Or does the unconditional progress showing that payment was received good enough for the GC? Reply
- Garret MuraiSeptember 26, 2016 Hi Chris. I’m a bit confused when you say you provided a “conditional progress that shows an exception amount” since the statutory conditional waiver and release upon progress payment does not include a space to include an exception amount. The only statutory waivers and releases which include a space for an exception amount (technically, disputed claims for extras) are the conditional and unconditional waivers and releases upon final payment. You may want to take a look at the sample waivers and releases we have on our the blog which also reference (at the top of each form) the Civil Code sections where you can find the statutory waivers and releases – https://calconstructionlawblog.com/toolbox/. Reply
- Christopher LeeSeptember 26, 2016 Hi Garrett, Thanks so much for your reply. The exceptions section I am referring to on the Conditional Progress lien release is a section that included on all templates. (an example template – https://www.rosendin.com/sites/default/files/PDF_Files/ConditionalWaiverAndReleaseOnProgressPayment.pdf ) The Exception part will state –
This document does not affect any of the following:
(1) Retentions.
(2) Extras for which the claimant has not received payment.
(3) The following progress payments for which the claimant has previously given a conditional waiver
and release but has not received payment:
Date(s) of waiver and release:________________________________________
Amount(s) of unpaid progress payment(s): $_____________________________
(4) Contract rights, including (A) a right based on rescission, abandonment, or breach of
contract, and (B) the right to recover compensation for work not compensated by the payment. Are you aware of this section I am referring to? I am referring to part (3) shown above.
- Garret MuraiSeptember 27, 2016 Chris. That was my bad. Provided that the “through date” is the same, your unconditional waiver and release upon progress payment suffices and there’s no need to send a revised conditional waiver and release upon progress payment.
- Tina B September 1, 2016 Hi Garret: Thank you for your very informative and helpful post. If a supplier does not file a preliminary notice for a public works project. Is it necessary to get a release from them? Will it hinder the contractor if a release is not requested? Thank you very much in advance. – T Reply
- Garret MuraiSeptember 2, 2016 Hi Tina. This is where the intersection of the law and practicality meet. There is an exception to the preliminary notice requirement for payment bond claims. Thus, to be safe, particularly on public works projects where payment bonds are often required, requiring that all subcontractors and material suppliers provide releases (irrespective of whether they served a preliminary notice) may be a prudent thing to do. However, general contractors often have numerous subcontractors and material suppliers on a project so getting a release from every subcontractor and material supplier of every tier can also be burdensome. Reply
- Miguel Franco Vinales August 8, 2016 Hi Garret,
Thanks for the article, very useful information. We are a general contractor and I was wondering if we should get lien releases from every single crew member from our subcontractors. I guess the question is, can a crew member of one of our subs file a lien against the owner if he doesn’t get paid by our sub? Reply
- Garret MuraiAugust 9, 2016 Hi Miguel. While laborers can record mechanics liens and, therefore, there is some logic in getting a waiver and release from laborers, it isn’t typically done and you would likely get some resistance from your subcontractors. Reply
- BARRYJune 7, 2016 Hi Garret,
We are a supplier of rigging and safety products to a job in California. There is no contract or agreement with our customer, who is based in Florida. The customer issues a verbal purchase order, often after we have provided a quote but sometimes without one. We deliver the items to the jobsite on our truck. Currently the customer has three checks that they want to mail to us as payment (in full) on three separate orders/invoices. They have sent us three Conditional Waiver and Release on Progress Payment forms for us to sign and return. We do this all the time and have no issue with it. However, they are requesting a notarized release form for each payment before they will release the check. And upon receipt of the check we are to mail (2) copies of each original signed, notarized, Unconditional Release Form back to them. This is a minimum of 2 notarized signatures per payment? We requested that they cover the notary cost of $10.00 per signature and so far they have refused, saying that California Law requires that the forms be notarized?
It is not so much the actual cost of the notary as it is the time involved having a key employee run to a notary for each payment.
Are we required to have the forms notarized? Reply
- Garret MuraiJune 7, 2016 Hi Barry. Thanks for reading. California’s statutory waiver and releases do not need to be notarized. Reply
- Miguel L MartinezAugust 18, 2016 Hi Garret, I somewhat in the same position as Barry in my Contractor wants all waivers notarized. (I do notice this is only asked of me when we are working on a military base though). However I put Through date of 6/31/16 instead of 6/30/16 and the company wants me to make the change which requires me to get the paper notarized all over again. This is another $10 + my wage + gas+ my time. I asked if their employee or I could just hand write in 0 but they are telling me no. Is it a huge deal if I just do it anyways? Thank you for your time, it is very appreciated.
- Garret MuraiAugust 21, 2016 Hi Miguel. There is no requirement under the Civil Code that waivers and releases be notarized.
- Sam May 25, 2016 We are a material supplier. What happens when a Sub uses a credit card to pay for materials and we have to supply an unconditional release? Most credit card transactions can be disputed with the credit card provider for up to six months. Reply
- Garret MuraiMay 26, 2016 Hi Sam. You raise a good and interesting point. I believe, however, that you typically only have 30 to 60 days to dispute a credit card transaction. Nevertheless, as you point out, you can run into problems if your customer pays you by credit card , you provide an unconditional waiver and release and the customer later disputes the credit card transaction. You can, of course, refuse to provide an unconditional waiver and release until 60 days (or, to be safe, 90 days) have elapsed from the time of the credit card transaction but this may not be a viable business transaction. The alternative is to simply prove up the credit card charge(s) in the event the customer disputes the credit card charge. Reply
- Melinda May 18, 2016 Hello, Loved reading your article Thank You – My understanding is in this order correct me if I am wrong. I am a person that LEARNS by scenarios….. If you could please review and Guide me in the correct order. (Contractor Liens) 1. With the BID you attach “Professional Lien? is there another name for the lien?
2. With the Bill you would attach “Conditional Lien” and also would use this form for request of Partial Payments? Confused the difference between conditional and unconditional? or would you use the unconditional lien for a Change Order?
3. “Pre Lien” is the next step and goes through a company?
4. “Professional Lien” is for Final payment?
5. Progressive Payments – should follow in the same order above? Much appreciate Melinda from San Diego. Reply
- Garret MuraiMay 18, 2016 Hi Melinda. Let me see if I can try to clarify things. First thing first, what are waivers and releases? By signing a waiver and release, as their name implies, you are waiving your right to record a mechanics lien, serve a stop payment notice or bring a claim against a payment bond for the amount stated and are releasing the party who is paying you from such claims. Importantly, a waiver and release only waives your mechanics lien, stop payment notice, and payment bond rights not any breach of contract claims you may have. Second, there are four types of waivers and releases and their use will vary depending on whether you are receiving a progress payment or final payment and will vary depending on whether you are anticipating payment or have already received payment. And, finally, there is how you use them. Suppose you are a subcontractor and perform work for a general contractor. Suppose further that you bill monthly and you start work on January and finish your work in March. At the beginning of February you issue your first invoice for work done in January in the amount of $10,000. Together with your February invoice you would send a conditional waiver and release upon progress payment for $10,000. In March you issue an invoice for $15,000, and assuming you were paid your February invoice, you would send together with your March invoice an unconditional waiver and release upon progress payment (for the $10,000 you were paid for your February invoice) and a conditional waiver and release upon progress payment (for the $15,000 you are owed in March). Finally, in April you issue your final invoice for $20,000, and assuming you were paid your March invoice, you would send together with your April invoice an unconditional waiver and release upon progress payment (for the $15,000 you were paid for your March invoice) and a conditional waiver and release upon final payment (for the $20,000 you are owed in April). After your final bill is paid you would then provide an unconditional waiver and release upon final payment indicating that you have been paid in full. That’s how it works. Reply
- Mike March 16, 2016 My company is a material supplier. We did work for a sub and have been paid in full over 6 months ago. The sub asks for unconditional progress releases every month for $0 dollars. Can I simply send them an unconditional final to release my lien rights so that I no longer need to fill out these unconditional progress releases every month? Reply
- Garret MuraiMarch 16, 2016 Hi Mike. I agree. If you’re done with your work and have been paid an unconditional final should be all they need. Reply
- Mike March 16, 2016 Thank you for your quick reply. And great article by the way. It’s nice to be able to find such a well written article to help with such an important aspect of asset protection.
- Garret MuraiMarch 16, 2016 Thanks Mike.
- Monica February 17, 2016 We are a subcontractor an accidentally listed the wrong dollar amount on the Unconditional Release (Progress) can we retract the release with the correct dollar amount? Reply
- Garret MuraiFebruary 17, 2016 The Code doesn’t address this situation but I would go ahead and send a revised (or amended) unconditional waiver and release in exchange for progress payment. Reply
- Brett Houser December 19, 2015 In the case wherein a progress payment was made and the GC , subs and all suppliers provided their conditional waiver and release and subsequently the pay application is disputed. The GC then submits the next pay application and conditional waivers and releases. What is the appropriate action the architect and owner should take in reviewing and processing the subsequent pay application? Reply
- Garret MuraiDecember 20, 2015 Hi Brett. Happy holidays. This is a prompt payment issue. Under Civil Code section 8800, a project owner can withhold up to 150% of any amount disputed in good faith without being subject to prompt payment penalties. So, if payment was made by the project owner, and it is later disputed by project owner, the project owner can withhold up to 150% of the disputed amount in the next pay application without being subject to prompt payment penalties. Reply
- MLCH December 9, 2015 If a financing company needs a lien waiver from a California-based construction company or manufacturer for a project that is located *outside* of California, do we still need to use the California form? Or is the CA form only relevant for projects located in-state? Reply
- Garret MuraiDecember 9, 2015 Hi. I got your telephone message as well. The California waiver and release forms only apply to projects located in California. Reply
- Arcy QUezada December 4, 2015 We are the owners of a project. I have a Sub that has suppliers on the job. I asked for Conditional Lien Waivers. The suppliers are not owed any monies at this time. The Sub provided me with Unconditional Progress releases with a Zero amount. I understood the Unconditional Progress releases to be a receipt of payment and always have an amount. Was I trained wrong? Reply
- Garret MuraiDecember 6, 2015 Hi Arcy. You are correct, unconditional waivers and releases are provided after payment, not before. However, they usually do not have an amount (unless there is a disrupted amount), and in the case of an unconditional waiver and release upon progress payment, include a “through” date. Examples of California’s statutory waivers and releases can be found on our blog under the “toolbox” menu, so that you can get an idea of what they do and don’t include. Reply
- Denise October 8, 2015 Hi. We are a GC and one of our sub contractors lost their license and insurance during the project. We paid them in full anyway and even took their employees on our payroll to finish the work. Now the sub contractor will not provide us with an Unconditional Final unless we sign a document stating that we will not go after them for the 20,000 we paid out above their contract amount. What do you suggest we do? Reply
- Garret MuraiOctober 8, 2015 Hi Denise. I can’t give you specific advice, but I would take a look first at your subcontract with the subcontractor to see whether they are required to provide waivers and releases. If so, and if they refuse to do so, they may be breach of contract. Reply
- Kay September 23, 2015 As a sub-sub, if the contractor above us, a sub of a GC pays us the appropriate payments on a job and asks me for an interim waiver on said job through the appropriate date, showing a zero balance, etc, but still has outstanding money with me on another job, can I refuse the waiver for job #1 as an incentive for him to satisfy his accounts on job #2. I do not believe that this is valid or legal, however others seem to think the practice is completely fine. If we have filed a preliminary NTO on a job, are we not obligated to complete the waivers as they pertain to each job as payments are made regardless of what outstanding issues we have with the sub on other jobs? Reply
- Garret MuraiSeptember 23, 2015 Hi Kay.In my view there are actually two questions here. First, can a contractor refuse to provide a waiver and release. And, two, if a contractor can refuse to provide a waiver and release, can that contractor refuse to provide a waiver and release on one project as means of getting paid by the same paying party on another project. As to the first question, unless your contract requires that you provide a waiver and release in exchange for payment, you are not required to provide one. Civil Code sections 8132, 8134, 8136 and 8138 – the waiver and release statutes – each begin by saying “if” a “claimant is required to execute a waiver and release in exchange for, or in order to induce payment of” a progress or final payment. So, unless required by contract, you are not statutorily required to provide a waiver and release. The second question is guided by the first. If you are required to provide a waiver and release, you can’t refuse to provide a waiver and release because you haven’t been paid on another project by the same paying party because you would be in breach of contract on the project in which you have been paid. There’s a pragmatic issue here as well, I think. If the waiver and release being requested is a “conditional” waiver and release, and you are required by contract to provide one, but you refuse to do so, how will you get paid? Alternatively, if it’s an “unconditional” waiver and release, and you are again required by contract to provide one, but you refuse to do so, who will you get paid your next payment? Moreover, under the waiver and release statutes, a “conditional” waiver and release automatically becomes an “unconditional” waiver release upon receipt of payment in any event, so threatening to not provide an “unconditional” waiver and release when you have already provided a “conditional” waiver and release, isn’t much of a threat. Reply
- JanJune 17, 2015 Are General Contractors allowed to make a Subcontractor reduce the amount they have progress billed and reduce the Conditional On Progress accordingly? Reply
- Garret MuraiJune 17, 2015 Hi Jan. I don’t understand your question. Generally, a pay application (whether for progress or final payment) will be accompanied by a conditional waiver and release in the same amount as the pay application. Reply
- JanJune 18, 2015 Correct. But some time later, maybe 45 days, the GC says they have to have us revise our invoice and conditional to a lower amount. My thought is they were approved less by the owner and want to reduce what we are going to be paid. I went to a class on lien some time ago and they made it clear that the owner or GC cannot dictate what you are progress billing. If they pay less than what the conditional is for what is the proper thing to do? Can they make us lower our invoice/cond release?
- Garret MuraiJune 18, 2015 Hi Jan. I’m still not sure I understand what is happening, but I agree you should not have to revise downward the amounts contained in your pay application or conditional waiver if the amounts represent work your company actually performed. Your pay application is your demand for payment, and the conditional waiver conditionally waives any mechanics lien, stop payment notice or bond claim rights you might have with respect to the amount contained in the pay application.
- JanJune 25, 2015 We progress bill around the 20th but project out what we think we will get accomplished by the end of month. If we bill for 75% but the GC says we are only approved for 65% can they make us change our billing and conditional lien? This is a particular problem if they wait too long to request/demand this because it messes up the billing for the next month as well. Am I making myself clear yet? I have had to revise, delete, void invoices for a few GC’s and I don’t think they have the right to make us do this.
- Garret MuraiJune 26, 2015 Hi Jan. If you are invoicing for work yet to be completed and there is a legitimate dispute that you have not accomplished the percentage complete you have invoiced for, then yes, the GC can ask that you revise your invoice and waiver and release. The GC doesn’t want you to “get ahead” of your actual percentage complete because the GC then runs the risk that you will walk off the job after you have actually only completed say 75% but have paid you say 90%. If, however, you believe you have actually completed the amount indicated in the invoice and waiver and release, you should then argue that with the GC.
- JanJune 30, 2015 I agree with you on that. But, they wait so long to dispute our invoice that I have already submitted the next months progress billing and it is difficult to alter at that point. Especially if it has been reported to the Board of Equalization – I won’t alter at that point.
I have told them they need to contact us sooner if they disagree with our % of completion.
- Keith DeBrine April 3, 2015 Hi Garret,
Here is a link to the progress unconditional lien waiver form. You’ll see that there is a location to list the specific dollar amount. Click to access UnconditionalWaiverAndReleaseOnProgressPayment.pdfReply
- Garret MuraiApril 23, 2015 Keith. My apologies for my delay getting back to you. You are absolutely correct. I was looking at an unconditional waiver and release on “final payment.” On an unconditional waiver and release on “progress payment” the amount you would insert would be the amount of the progress payment you received for the earlier conditional waiver and release on progress payment which you provided, not the sum total of all progress payments received to date. So, in your hypothetical, it would be the $5 not the $15. Reply
- Keith DeBrine April 1, 2015 Garret,
A question that has arisen – On Progress unconditional lien wavier for payment #2: does the amount need to be cumulative or should it be for the amount of the prior pay application? For example: Pay Application #1 is for $10.00. Pay Application #2 is for $5.00. So should the amount of progress unconditional lien waiver you receive with Pay Application #3 be for $5 (the amount of Pay Application #2) OR Should it be for $15.00 (the cumulative amount of all previous Pay Applications that have been funded?)
Thanks
Keith Reply
- Garret MuraiApril 2, 2015 Hi Keith. There is no place to put a dollar amount in the “unconditional” releases. Rather there is a “through date,” meaning that the party signing the unconditional release is waiving the ability to make a statutory payment remedy claim for work performed “through”‘the date indicated. The through date is typically the last date work was performed as indicated in the immediately preceding pay application. Reply
- debraMarch 14, 2018 The ca unconditional progress release does have a place for the dollar amount, at the end of the big paragraph bottom right
- Garret MuraiMarch 15, 2018 Yes, agreed, but not on the unconditional final.
- Ronny McNamaraMarch 3, 2015 Hi Garret, You have very appropriately covered these vital documents with an easy to understand example. But these forms are great when every thing is fine with the world, contractors and sub contractors are doing their job and getting paid by the owner timely, at the end every body is happy. Problem arises, when owners and prime contractors start defaulting on payments. Reply
- Garret MuraiMarch 4, 2015 Hi Ronny. Absolutely right. There are numerous scenarios where something can go wrong, which for that very reason, we can’t cover every scenario here. That’s when you need an attorney (wink, wink). Reply
- Mark HuberFebruary 18, 2015 Would it not be more appropriate that the “Through Date” be the last date goods or services are rendered rather than the date of the pay application (in your examples March 1, 2015)? Typically, the date of our invoice is days later that the last date we performed services on the project site. Reply
- Garret MuraiFebruary 18, 2015 I agree with you Mark. Poor word smithing on my part. I will revise. Thanks for reading! Reply
- Josh Cohen February 11, 2015 Clear and concise. Are you sure you’re an attorney? Also, 12 is more like 2.5 handfuls. Reply
- Garret MuraiFebruary 11, 2015 Thanks Josh. I think RI and DE might be included, so let’s split the difference and say 1 3/4 handfuls. Reply
- Darren ChakerFebruary 9, 2015 Very detailed post about waivers. Thank you for taking the time and effort to be so thorough! Reply
- Garret MuraiFebruary 9, 2015 Thanks Darren. And thanks for reading. Reply
- Leona August 9, 2016 I have a question regarding waivers, can someone add late fees and finance charges on a lien release? Thank you Leona
- Garret MuraiAugust 11, 2016 Leona, that’s a very good question but, unfortunately, I don’t have an answer for you. The waiver and release statute doesn’t address whether you can include late fees and finance charges in a waiver. If I were a judge though, and not just an attorney, I would say you can’t and here’s the reason why: a waiver and release waives and releases a party’s right to record a mechanics lien, serve a stop payment notice and make a payment bond claim, and when recording a mechanics lien you are only allowed to claim the lesser of (1) the reasonable value of work provided by a claimant; and (2) the price agreed to by the claimant and the person that contracted for that work. Somewhat similarly, a stop payment notice can only include in a stop payment the amount due the claimant for work provided through the date of the notice. The payment bond statue is silent on the amount claimed. Thus, the amount you can claim when recording a mechanics lien and serving a stop payment notice would not allow you to claim late fees and finance charges, and thus, I would say that neither can you include late fees and finance charges in a waiver and release.
- Ann March 22, 2016 We are a General Contractor. One of our Sub-Contractor provided us an Unconditional Progress Release through the current invoice date which I haven’t paid the invoice yet. the Unconditional progress release indicated that the claimant has received the following progress payment: $0.00. My question is do I (as the General Contractor) still need to request the Sub-Contractor for a Conditional Progress release through the current invoice date? Even though it’s going to be 0.00 amount on the release? Reply
- Garret MuraiMarch 24, 2016 Hi Ann. Thanks for reading. I may not be understanding the scenario completely but it sounds like the sub doesn’t know when to provide the proper release. Assume, for example, you get a pay app from the sub for $100, to keep things simple. In addition to the pay app the sub should be providing a conditional waiver and release upon progress payment indicating that once it receives a check for $100 that it will waive and release any statutory construction payment claims. Assume then, that you pay the sub $100, and the following month the sub submits another pay app but this time for $200. In addition to the pay app the sub should be providing: (1) an unconditional waiver and release upon progress indicating that it received payment for the previous month’s pay app of $100; and (2) a conditional waiver and release upon progress payment for the current month indicating that once it receives $200 that it will waive and release any statutory construction payment claims. As you’ve indicated, it seems that the sub is providing an unconditional waiver and release upon progress payment indicating “$0” paid, when it didn’t provide a conditional waiver and release upon profess payment FIRST indicating that IF it is paid its pay app that it will waive and release any statutory construction payment claims it may have. In short, it sounds like the sub is providing an “unconditional” before providing a “conditional,” which is backwards.
- Jan March 28, 2016 As a subcontractor, I have skipped the Conditional and provided an Unconditional Progress Release for $0.00 when I know I don’t have any billing for that month and there isn’t any money due to us.
- Garret MuraiMarch 28, 2016 Hi Jan. Perfectly fine to do it that way so long as you are aware that an unconditional for that month is, as it’s name suggests, “unconditional.”
- T. Lo June 15, 2016 Hi Garrett, We are a manufacturer and get asked for waivers often, my question is about an “Unconditional Waiver and Release on Final Payment”. If they are fully paid do i put $0.00 on exceptions “disputed ” claims? Reply
- Garret MuraiJune 22, 2016 Hi T. I assume by “they,” you actually mean “we,” since you are the one who is being asked to provide the release. If so, and you have been fully paid and have no claims, then you would put down zero dollars.
- Keevin Blue July 28, 2016 I agree with Darren, this was excellent. However, I do have a circumstance that was not addressed (or I didn’t get it). On a certain job, I issued 2 conditional progress waivers for two billings which since have been paid. Apparently, the GC we were under quit the job and now is asking for an unconditional final. They owe us no money, but my question is do I issue and unconditional progress or final waiver? Reply
- Garret MuraiJuly 28, 2016 Hi Keevin. Thanks. It depends on whether your scope of work is complete and, if not, whether you are going to complete your scope of work (since the GC you had a contract with is no longer on the project). If your work is complete or, if not complete, will not be completed (b/c the GC you had a contract with is now off the project), then I suggest an unconditional final. If your work is not complete but it looks like you may complete the work (for example, because your contract is being assigned), then I suggest an unconditional progress so as not to confuse the owner and others when you start to issue conditional progress waivers again.
- Keris August 9, 2016 Hi Garret, I have a quick question. We are a mechanical contractor that does business nationwide, but currently working on a project in CA. Our GC is asking for $0 waivers for one of our subs’ vendors that is not yet billing on this project. We have told the GC that the vendor has no open invoices; further, this is cited on our subs’ sworn statement. However, the GC is stating that we are required to submit a $0 waiver every month until the vendor has been paid in full simply because they have filed a preliminary notice on the project. To your knowledge, is this information accurate? On projects in different states, I only am only required to provide lower tier waivers if the current net of any one period’s billing exceeds $10K. Is this different in CA? (Where can I find information on this?! Please help! Thank you!) Reply
- Garret MuraiAugust 9, 2016 Hi Keris. Unfortunately California’s waiver and release statutes don’t specify “how” to use waivers and releases, only that any waiver and release (if required in your contract) use language that is substantially the same as that set forth in the statutes. However, typically, a waiver and release is only required when a contractor, subcontractor, material supplier, or equipment lessor has provided work, materials, or equipment. Thus, if a subcontractor serves a preliminary notice but has yet to perform any work a waiver and release is typically not required of the subcontractor because the subcontractor has not performed any work, has therefore not billed for any work, and there is no need for a waiver and release because there is no concern that the subcontractor will record a mechanics lien, serve a stop payment notice, or make a bond claim. However, you specifically said that the GC is requesting a waiver and release from from a “vendor” which makes me think that the “vendor” is a material supplier. If so, the material supplier likely wouldn’t have served a preliminary notice unless the material supplier had provided materials on the project, in which case, it would make sense for the GC to ask for a waiver and release so it can confirm that the material supplier has been paid.
- Tenisha Mayfield August 17, 2016 Question: We are a contractor and our subcontractor supplier gave us an unconditional Waiver for final payment for a project that is nearing completion. The supplier had a 20 day prelien that was satisifed. If the subcontractor does additional work say time and material work and used the same supplier for the same job as before do the unconditional final payment from the supplier suspersedes the prior unconditonal final payment? or do the supplier needs to submit another prelien for the new work? Reply
- Garret MuraiAugust 18, 2016 Hi Tenisha. Good question and one that wades into the weeds of the waiver and release statutes. Unfortunately, the there are a number of scenarios that the release statutes don’t address and your situation is one of them. Here’s my thoughts on it though: It depends on whether the “additional work” you make reference to is being performed by way of a change order or if it is truly additional or extra work. When you think about it you can add scope to an existing contract by way of a change order or you can add scope by entering into a new contract altogether. In the former situation, there is only one contract (the original contract) and in the latter situation there is a second contract (the new contract). If additional scope is added to an existing contract then, arguably, a new preliminary notice wouldn’t be necessary. However, if additional scope is added by way of a new contract, the supplier would, again arguably since the statutes don’t address this, need to serve a new preliminary notice. But there’s one other wrinkle as you point out, if it is change order work and the supplier has already provided an unconditional waiver and release upon final payment, what is the supplier to do if it is not paid for this change order work? Has it waived its statutory rights? My belief is that equitably it hasn’t because when the supplier provided the unconditional waiver and release upon final payment it had in fact been paid in full for all work within its original scope, and it would be inequitable to add scope by way of a change order, not pay the supplier, and then argue that the supplier’s earlier unconditional waiver and release upon final payment bars the supplier from recording a mechanics lien, serving a stop payment notice, or making a bond claim.